Day 145. Shoulder High

Paul does some sterling work in moving the soil heap and filling in the edges of the building where the hole met the blockwork. Good. Now (sometime) the gravelly bit needs to be restored. Or remade.

The blocks are up to shoulder high when I get back past 4. Fairly soon they will need some scaffolding to get any higher. Looking inside, I can see that the insulation is being retained against the inner wall by little ties and disks so it will stay in place. Pete phones up ?Bob? to check that the doorways seem wide, but yes this is correct, as we expected.

Also the bricks are extensively stacked where they are working, so I think we're down to only one stack in the driveway. Err, and some blocks...

We had pondered going to Ikea tonight or sometime, but this is not possible, as Ian hasn't done the kitchen plans and is off to France for a few days. Hmm.

Meanwhile invoice number ?7? arrives together with Ians OK note.