Thursday, October 27, 2005

Day 146. Floor High

Running out of suitable words for high. Today is a lovely warm sunny day, perfect for building (or indeed for anything else).

The wall has reached about to the level of the floor on the first floor, so Pete needs to do some measuring to make sure that the floor joists are going to go across at about the right level. Also the narrow slit windows that will have frosted glass are beginning to appear.

Speaking of which... having (briefly) had a nice clear drive we get two bags of sand turn up, then later some more blocks, on top of which may lay the joists.

Pete has "folded" the walls round for where the door frames will be. Something that I suppose must be a vertical damp course goes in between - I must ask him what this is for.