Day 320-2. Plaster and Paint

Friday: Pete and Tim come to board over and then plaster the nominally-ex kitchen ceiling. We're not quite down to totally disrupted in there, but its close.

Monday: nowt. This is *rather* annoying. Complain.

Tuesday: painters turn up. They think they are here just today, and back to Norfolk tomorrow. Complain. Bob says they are here until finished: good; lets hope its so. Meanwhile, order flooring (£4k) of "engineered board" as its called: 20mm, of which the top 3mm is oak. Painters are doing the "music room" as we grandly call it; they have to shuffle out various boards that are in the way. They also get some of the ooutside started, hurrah.

Still no sign of the gutters, though.