Day 345-350. Mostly painting

Mostly painting this week, and we're mostly finsihed now. As I believe is traditional, they are leaving a few irritating bits of stuff unfinished but hopefully will get done sometime.

Tim has boxed in the electric and gas meters in the hallway, making a rather nice looking cupboard out of it faced in the floorboards. Les the tiler has tiled the bath end in his standard not-exactly-brilliant fashion; and it needs some filler to stop leaks; but it will do.

Remaining: tidy up outside; a bit more painting (esp the stairs); uncover the stair treads; and do the floorboards at the top of the stairs. A days work if they actually set to doing it - any guesses for how long in practice?